Conway-Perry Road Transmission Line Project

Conway-Perry Road

Overview

Transmission studies indicate that under certain contingencies, the Bucksville-Perry Road 230 kV lines can overload. Establishing a transmission line between Conway and Perry Road will mitigate these contingencies. Santee Cooper plans to construct the new Conway-Perry Road 230 kV line by rebuilding the Conway-Carolina Forest 115 kV line as double-circuit 230/115 kV in the existing right of way. From the intersection point of the Conway-Perry Road and Conway-Carolina Forest 115 kV lines, the remainder of the Conway-Perry Rd 115 kV line will be constructed as double-circuit 230/115 kV line in the existing right of way. Together this will combine for 9 miles from the Conway Switching Station to the Perry Road Substation. This will benefit residents and businesses by providing stability, increasing electric reliability, and increasing resiliency. The new line is subject to the most up-to-date standards and codes, making it more resilient than the current line. The project is currently in design with some station upgrades and transmission work projected to begin no later than August 2024.

FAQs

The project will stretch from the Conway Switching Station to the Perry Rd Substation.

See Map

The overall length of the project is 9 miles.

2023- The project will be designed and the Public Service Commission process started

2024- We anticipate PSC approval in early 2024 and to receive materials for the rest of the year. Some work may begin in the 3rd quarter of 2024 to avoid turtle, bat, and other wildlife mating seasons.

2025- At the latest, transmission and substation construction is anticipated to be ongoing throughout most of the year.

Minor activities will occur in 2023, such as soil borings and survey work. Perry Road Substation work is tentatively scheduled to occur in 2024, with Conway Switching Station perhaps as soon as Q1 2024. Reestablishing the right of way, if and as needed, would begin in 2024. Transmission construction would begin from Q3 2024 to early January 2025 and end in the autumn of Q4 2025. The project is scheduled to be in service on Dec. 1, 2025.

The new transmission line structures are in the design process. The intent would be to use new steel structures, built to modern codes and regulations for this region and wind zone. Many of the structures currently in place along this route are wood poles from 1952 and 1968, except for a few which were replaced for various reasons throughout the years.

This project will increase the amount of power able to the delivered in the system. As the population grows in this area, increasing the available power is critical both now and in the future. The new structures will be more resilient to storms and other natural disasters. The intent is to utilize existing right of way, so we only anticipate needing an extra 0.5 acre at the Perry Road Substation to complete this project and less than 0.1 acre at the Conway Switching Station. Overall, this project will deliver more power in a more reliable way.

The project is currently on time and is in the design and approval phase.

We used existing right of way and a shorter route to lessen the impact to residents and stakeholders, and decrease distance, time and costs. There was a “Northern Option” of rebuilding the entire Conway to Perry Road line instead of the selected route (the “shortcut”) of using the existing Conway to Carolina Forest and then the existing Conway to Perry Road. This was not chosen because of increased cost and distance.

Landowner notifications were sent to people who share a boundary with the project in late 2022. We intend to file for all public permits that apply as we reach those stages of the project.

There are a few reasons why underground lines are not being considered for this project. Underground lines can be more intrusive to the environment, depending on where they’re placed, and it’s more intrusive to the environment when they need to be repaired. Underground lines typically cost more than the amount overhead lines cost, and they would take a much longer period of time to repair when there is an issue.

Yes. We considered five different scenarios for this project. The first was “no build.” This was not a viable option according to internal studies and growth in the area. The second was “greenfield”, which would have meant an entirely new line and entirely new right of way. Due to the densely populated area this project goes through and the sensitive environmental areas nearby, this would have been much more expensive project and impacted the environment much more. The third option was rebuilding all of Conway to Perry Road (what we referred to as the “Northern Option”). This would have resulted in a project that covered more distance, cost more, and impacted more stakeholders. The fourth option is considered the best option, using the existing Conway to Carolina Forest right to way to meet the existing Conway to Perry Road right of way. The fifth option was Bucksville to Perry Road, but almost all of that is wetlands and it would have been the most expensive of all of the options.

This project will use existing right of way and should only include the need to add less than 0.55 acre of land near the Perry Road Substation and Conway Switching Station.

With a rebuild on existing right of way such as this, impacts, if any, are much more limited than new construction. Several cultural, social, and environmental studies are in progress for the project currently. We will implement best management practices to protect freshwater and tidal wetlands. Besides the very small footprint of the replacing transmission poles, reestablishing our existing right of way, and identifying danger trees, no further impacts are expected along the route. The small 0.5-acre section near the Perry Road substation will be cleared to expand that station, which is about the size of one small house lot. That area is uninhabited.

Santee Cooper and our consultant, Burns and McDonnell, are in the process of complying fully with all regulatory requirements. Updates will be posted here as progress is made in this area. Our goal is to be fully permitted by Aug. 1, 2024, and Public Service Commission approval is expected no later than Jan. 31, 2024.