Navigate this section

Cross

Cross Station has 2 ponds and 2 landfills subject to elements of the CCR Rule.  The Cross Gypsum Pond was certified closed by removal on March 11, 2017 and the Cross Class 2 Landfill was certified closed on February 28, 2017.

Bottom Ash Pond

Because Santee Cooper is closing the Bottom Ash Pond by removal, this unit is not subject to post-closure care requirements in 257.104.

Santee Cooper is closing the Bottom Ash Pond by removal and does not plan to retrofit this unit into a new CCR surface impoundment; therefore, these criteria are not required.

Closed Gypsum Pond: Certified Closed by Removal on March 11, 2017.

The Gypsum Pond was closed by removal of CCR material and CCR-contact soil under a South Carolina Department of Health and Environmental Control (SC DHEC) approved closure plan on March 11, 2017.

Click below to expand each section to get to specific documents.

Existing surface impoundments were required to complete the Location Restrictions demonstrations no later than October 17, 2018. Because the Gypsum Pond was certified closed by removal on March 11, 2017 and could no longer contain CCR or liquids, these demonstrations were not completed.

 
Existing surface impoundments were required to complete the above Design Criteria demonstrations no later than October 17, 2016. Because all CCR removal from the Gypsum Pond had been completed by this date, and the pond could no longer contain CCR or liquids, these demonstrations were not completed.


Existing surface impoundments were required to prepare the Fugitive Dust Control Plan and initiate annual inspections no later than October 19, 2015. The Initial Inflow Design Flood Control Plan was required no later than October 17, 2016. Because all CCR removal from the Gypsum Pond had been completed by October 17, 2016, and the pond could no longer contain CCR or liquids, these demonstrations were either not completed or are no longer necessary.

Because the Gypsum Pond was certified closed by removal on March 11, 2017, this unit is not subject to post-closure care requirements in 257.104.

Class 2 Landfill Certified Closed on February 28, 2017.

Click below to expand each section to get to specific documents.

Existing landfills were required to complete the Location Restriction demonstration no later than October 17, 2018. Because the Class 2 landfill was closed on February 28, 2017, this demonstration was not completed. However, this demonstration was completed for the adjacent Class 3 Landfill which demonstrates compliance.

Because the Class 2 Landfill was closed on February 28, 2017, the Fugitive Dust Control Plan and Annual Fugitive Dust Reports are no longer necessary.

Class 3 Landfill

Click below to expand each section to get to specific documents.

  • 257.90(e) - Annual Groundwater Monitoring and Corrective Action Report
  • 257.91(f) - Certified groundwater monitoring system
  • 257.93(f)(6) - Certified selected statistical method
  • 257.94(e)(3) - Notification when assessment monitoring is established
  • 257.95(e) - Notification to resume detection monitoring if results for Appendix III & IV constituents are below background
    • Demonstration to be completed as needed
  • 257.95(g) - Notification if Appendix IV constituents have exceeded groundwater protection standards at statistically significant levels
    • Demonstration to be completed as needed
  • 257.95(g)(5) - Notification if Assessment of Corrective Measures has been initiated 
    • Demonstration to be completed as needed
  • 257.96(d) - Assessment of Corrective Measures Report
    • Demonstration to be completed as needed
  • 257.97(a) - Semi-annual progress reports for selecting and designing a remedy and the final Remedy Selection Report
    • Demonstration to be completed as needed
  • 257.98(e) - Notification that the remedy is complete
    • Demonstration to be completed as needed

  • 257.102(b) - Written Closure Plan
  • 267.102(e)(2) - Demonstration + owner certification for time extension to initiate closure if idle for 2 years
    • Demonstration to be complete as needed
  • 257.102(f)(2) - Demonstration + owner certification for time extension to complete closure
    • Demonstration to be complete as needed
  • 257.102(g) - Notice of intent to close CCR unit
    • Demonstration to be complete at initiation of closure
  • 257.102(h) - Notice closure is complete with PE certification
    • Demonstration to be complete within 30 days of completion
  • 257.102(i) - Notice deed notation was recorded for units closed in place
    • Demonstration to be complete within 30 days of completion
  • 257.103(c)(2) - Annual progress under alternative closure
    • Demonstration to be complete in 13 months after NOI
  • 257.104(d) - Written Post-Closure Plan and any amendments
  • 257.104(e) - Notification post-closure is complete
    • Demonstration to be complete within 60 days of post-closure being completed